Michigan sets well and building codes, but the parcel evidence for a private well and residential septic system usually lives with the local health department. Near water, an EGLE permit layer may change the site entirely.

Start with records

Ask for permits, not memories.

Before pricing a replacement or accepting a seller’s description, request the local health department’s well permit, final approval, water results, septic permit, site evaluation, design and repair history. Then compare them with what is physically present.

well permit Wellogic record water tests septic permit approved plan final inspection

Two systems · one local counter

The health department decides whether the parcel can support the plan.

01 / WATER

Permit before drilling

Michigan’s state well code sets construction and pump standards. EGLE says every county requires a local health-department permit or notification before drilling, and county ordinances may be more stringent.

  • registered contractor and permit conditions
  • location and isolation from contamination
  • construction record within the required timeline
  • yield, quality and abandoned-well closure
Use EGLE’s contractor guide
02 / WASTEWATER

Site approval is local

Individual residential septic systems are typically permitted and inspected by the local health department. EGLE supports local programs; larger capacity and discharge situations can shift into state programs.

  • soil profile and seasonal water table
  • system footprint and replacement area
  • bedroom/design flow assumptions
  • local alternative-system and maintenance rules
Review the state program boundary
MAP?

Wetlands and shore work

A map can flag risk. It cannot clear the lot.

EGLE says an onsite inspection is always necessary to determine wetland presence with certainty; inventories and aerial imagery do not establish parcel boundaries. Regulated wetland work can include filling, dredging, building, development and drainage.

1,000 ft Great Lakes / Lake St. Clair proximity category
500 ft inland lake, pond, river or stream proximity category
>5 ac one category for otherwise isolated wetlands

Those distances describe categories in the state framework, not automatic parcel determinations. Connectivity, size, site conditions and other statutory tests matter.

Read EGLE’s property-identification guidance

Home and legal occupancy

Find the enforcing agency.

Michigan’s Residential Code governs one- and two-family dwelling construction. Enforcement may be by the state, county or local unit, so LARA directs applicants to the current statewide jurisdiction list before filing.

  1. 01 Confirm zoning, lawful parcel, setbacks, access and dwelling classification.
  2. 02 Submit the building permit and required construction documents to the correct enforcing agency.
  3. 03 Obtain plumbing, mechanical and electrical permits from their respective authorities.
  4. 04 Schedule required inspections before covering work.
  5. 05 Obtain final approval or certificate of occupancy before residential use.
Owner-builder

Licensing law has exceptions, but owning the land does not waive permits, code or inspection.

Tiny / alternative home

Ask how the proposed unit is classified before relying on size, mobility or factory construction.

RV occupancy

No statewide blanket permission was established. Local zoning, time limits and sanitation control the parcel answer.

Private-water responsibility

Clear water is not a laboratory result.

Michigan identifies the private-well owner as ultimately responsible. Current state guidance recommends annual coliform/E. coli and nitrate/nitrite testing, arsenic and lead every three to five years, and at least one PFAS test—then additional analytes for local risks.

yearly bacteria · nitrate / nitrite 3–5 years arsenic · lead at least once PFAS after event flood · repair · quality change

A mortgage test or old final approval is a snapshot, not a continuing warranty of potability or capacity.

Michigan buyer checkpoint

Make the systems fit before closing.

Boundaries

Survey, legal access, zoning, township/city, health jurisdiction and private restrictions.

Land/water interface

Wetland identification, floodplain, shoreline, dunes/erosion where relevant, and access crossing.

Water

Permit and Wellogic record, inspection, yield, risk-based lab panel and treatment budget.

Septic

Approved plan, field location, condition, design capacity, reserve area and local upgrade trigger.

Dwelling

Classification, enforcing agency, permit set, trades, winter design and occupancy.

Temporary use

Written answer for RV/camping or construction occupancy, including sewage and water.

Use the complete property checklist

Evidence ledger

Official Michigan sources

Reviewed September 26, 2026. Local permit dependence is stated plainly; mapping is never presented as a wetland determination.

  1. MI1
    Water Well Construction

    Michigan EGLE · State well code, contractor and health-department framework

  2. MI2
    Consumer’s Guide to Hiring a Well Contractor

    Michigan EGLE · County permits, Wellogic records and buyer questions

  3. MI3
    Onsite Wastewater Management

    Michigan EGLE · Local-health review and large-system assistance

  4. MI4
    Learn About Wastewater

    Michigan EGLE · Residential local permits and EGLE discharge programs

  5. MI5
    Building Permit Information

    Michigan LARA · Residential code, enforcement agency and occupancy

  6. MI6
    Are There Wetlands on My Property?

    Michigan EGLE · Inventory limitations and onsite determination

  7. MI7
    State and Federal Wetland Regulations

    Michigan EGLE · Regulated wetland categories and permit activities

  8. MI8
    Resources for Private Residential Well Owners

    Michigan EGLE / MDHHS · Risk-based testing schedule and owner responsibility